Domain 1: Robot safety rules

Question 1

Jam clearing requires access between a pneumatic gripper's jaws. An authorized employee has locked out the electrical disconnect and verified electrical isolation. The gripper still supports a workpiece, and its pressure gauge remains above zero. Before anyone reaches into the jaws, which additional control is required?

Show answer & explanation

Correct answer: C - Secure the load, isolate the air supply, dissipate stored pressure, and verify isolation.

Domain 2: Robot types, components and end-effectors

Question 2

An assembly robot positions parts using two linked horizontal arms that rotate about parallel vertical axes. A vertical slide and a wrist-rotation axis complete the tool motion. What type of robot is the operator using?

Show answer & explanation

Correct answer: D - SCARA

Domain 3: Normal startup and shutdown

Question 3

Production is ending normally, with no hazard or fault present. The cell procedure states that CYCLE STOP completes the current cycle, leaves the gripper empty at the parking point, and prevents another cycle; HOLD pauses immediately at the current instruction. A part is currently in transfer, and a validated, authorized point correction is still unsaved. Which shutdown sequence fits this situation?

Show answer & explanation

Correct answer: A - Request CYCLE STOP, confirm the empty parked state, save the correction, then perform controller shutdown.

Domain 4: Emergency shutdown and recovery

Question 4

A cell is specified to use a category 1 emergency stop. During its controlled acceptance test, actuator power remains available while the robot decelerates, then is removed at standstill. Releasing and resetting the emergency-stop device does not restart the robot. Which conclusion belongs in the test record?

Show answer & explanation

Correct answer: B - The observed sequence matches category 1 stopping and prevents restart from reset alone.

Domain 7: Teach-pendant menus and status indicators

Question 5

A robot has stopped moving, and an operator highlights UNLOAD_B in the program directory. The execution screen still reads ACTIVE PROGRAM: LOAD_A; STATE: WAITING; WAIT CONDITION: FIXTURE_READY=1; ACTUAL FIXTURE_READY: 0; ACTIVE ALARMS: NONE. What does this display establish?

Show answer & explanation

Correct answer: D - LOAD_A remains active and is waiting for the fixture-ready input.

Domain 11: Robot position in five frames

Question 6

A maintenance record requires the current TCP position in World coordinates. The pendant shows User coordinates (40, 15, 20) mm. The User origin is at World (500, 100, 50) mm; User +X points along World +Y, User +Y along World -X, and User +Z along World +Z. The robot remains stationary. Which World position should be recorded?

Show answer & explanation

Correct answer: B - (485, 140, 70) mm

Domain 12: Frame definition using the three-point method

Question 7

A frame-teaching wizard requests an origin O, a point defining +X, and a third point on the positive-Y side of the intended XY plane. Using the verified TCP, the operator records World positions O=(0,0,0), X=(160,0,0), and P=(160,120,0) mm. A colleague insists that P must lie on the Y axis through O. How should these data be assessed?

Show answer & explanation

Correct answer: C - The points define the intended axes; P establishes the plane without lying on the Y axis.

Domain 14: Digital robot input/output testing

Question 8

An unloaded gripper is undergoing an authorized I/O test with the robot stationary. Its OPEN and CLOSED inputs indicate only the two ends of jaw travel. The test requires CLOSED to become 1 within 1.0 second of a close command. After 0.3 seconds, both inputs are 0, the jaws are visibly closing, and there is no obstruction. How should the operator interpret this snapshot?

Show answer & explanation

Correct answer: A - Travel is still in progress; monitor for closed confirmation within the allowed time.

Domain 17: Robot point teaching and adjustment in the appropriate frame

Question 9

A dispensing nozzle has been replaced with a longer one. The mounting is secure. During a low-speed check, the operator jogs the new tip to a fixed reference mark, then commands orientation changes about the selected tool center point (TCP). The physical tip sweeps away from the mark even though the displayed TCP position remains constant. Before touching up the taught points, what should be checked?

Show answer & explanation

Correct answer: C - Whether the active TCP definition matches the replacement nozzle

Domain 18: Robot fault identification and recovery

Question 10

Two pneumatic grippers supplied by the same air manifold fail to reach their closed positions during separate tests. Both close-command outputs are ON, and both closed-position inputs remain OFF. The manifold gauge reads 330 kPa; the equipment requires 400-600 kPa. No electrical or robot-motion fault is reported. Where should the fault investigation begin?

Show answer & explanation

Correct answer: D - The shared pneumatic supply and its out-of-range pressure

The rest of the C-215 blueprint

The C-215 exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more C-215 questions with explanations.

Continue in the free practice test →

View plans